§ 56-8.410. Issuance.  


Latest version.
  • (a)

    Permits shall be issued within the following time limits:

    (1)

    Permits not requiring traffic control exceeding three minutes shall be issued within two working days of completion of application.

    (2)

    Permits requiring traffic control exceeding three minutes shall be issued within four working days of completion of application.

    (3)

    Permits requiring road closures shall be issued within ten working days of completion of application.

    (b)

    An application shall not be deemed complete until all required information is provided, all fees are paid, the application is properly signed, and evidence of adequate insurance coverage is provided to the director of general services.

(Ord. 96-39 § 2).