§ 58-4.812. Existing poles and conduits.  


Latest version.
  • To the extent possible, a cable operator shall use existing poles and conduits within the public rights-of-way in installing its cable system. If such poles and conduits are unavailable, then a cable operator shall construct its own wireholding structures within the public rights-of-way, and install its facilities in those structures, provided there is sufficient room for additional structures in the public rights-of-way. Where the public rights-of-way cannot be used, a cable operator shall, to the extent possible, use existing poles and conduits located outside the public rights-of-way, after obtaining any necessary authorizations. In no case may additional poles or other structures be installed in the public rights-of-way or on any public property without the prior permission of the county.

(Ords. 2006-65 § 3, 93-55).