§ 716-6.006. Regular development requirements.  


Latest version.
  • (a)

    The county building official, upon notification from the permittee or his agent, shall inspect the work at the following stages of the work and shall either approve the portion then completed or shall notify the permittee or his agent wherein it fails to comply with the requirements of this division:

    (1)

    Initial. When the site has been cleared of vegetation and unapproved fill and has been scarified, benched or otherwise prepared and before any fill is placed;

    (2)

    Rough. When rough grading has been completed and approximate final elevations have been established; drainage terraces, swales and other drainage devices graded ready for paving; and berms installed at the top of slopes;

    (3)

    Final. When work has been completed, all drainage devices, systems and facilities installed and slope planting established.

    (b)

    In addition to the called inspections specified above, the county building official may:

    (1)

    Make such other inspections as he deems necessary to determine that the work is being performed in compliance with the requirements of this division; and

    (2)

    Require investigations and reports by a soil engineer and/or engineering geologist.

(Ords. 99-46 § 11: 69-59 § 1, 1969).