§ 88-11.816. Progressive reclamation.  


Latest version.
  • Reclamation of mined areas shall take place as soon as practicable following completion of surface mining operations. When simultaneous or concurrent reclamation is practicable, the reclamation plan shall include a timetable for commencing and completing such reclamation and shall include (a) the beginning and expected ending dates for each phase; (b) all reclamation activities required; (c) criteria for measuring completion of specific reclamation activities; and (d) estimated costs for completion of each phase of reclamation.

(Ords. 2000-18 § 7; 79-1 14; Pub.Res.C. § 2772(f)).