§ 88-22.602. Permit—Required.  


Latest version.
  • (a)

    A land use permit is required to establish, maintain, or expand a permanent meteorological tower.

    (b)

    A temporary meteorological tower permit is required to establish, maintain, or expand a temporary meteorological tower. An application for a temporary meteorological tower permit must comply with the special permit provisions of Article 26-2.20 and will be considered under the administrative decision procedure specified in Article 26-2.21.

    (c)

    A temporary meteorological tower permit may be extended once for a period of up to six months, as long as the application to extend the permit is submitted at least thirty days before the permit expiration date. A temporary meteorological tower operating under a temporary meteorological tower permit extension is not a permanent meteorological tower.

    (d)

    If an application for a proposed temporary meteorological permit does not demonstrate that the tower will comply with the development standards in subsection (a) of Section 88-22.406, the applicant may apply for a land use permit to modify those development standards.

(Ord. No. 2013-17, § II, 8-13-13)