§ 88-3.412. Permit—Information requirements.  


Latest version.
  • The application shall be accompanied by the following:

    (a)

    A site plan including the following in- formation:

    (1)

    Existing topography, trees, and drainage channels,

    (2)

    Direction of prevailing winds across the project site,

    (3)

    Location, height, and dimensions of all existing and proposed structures and fencing,

    (4)

    Location and height above ground of all proposed WECS and aboveground utility lines,

    (5)

    Location, grades, and dimensions of all temporary and permanent on-site roads,

    (6)

    Preliminary grading for all roadways, structures, WECS sites, and other site work,

    (7)

    Distance to all residences, public and private airports and airstrips, schools and any other uses, as determined by the community development director within one mile of all exterior project boundaries;

    (b)

    A scale profile drawing of the subject site and proposed WECS as seen from the nearest public road and the nearest scenic route;

    (c)

    A projection of the annual production (kwh) of the total WECS project at full buildout;

    (d)

    A regrading and revegetation program for temporary roadways no longer needed after project construction:

    (e)

    A preliminary erosion, drainage, and sediment collection and control plan;

    (f)

    A reclamation plan consistent with Article 88-3.8;

    (g)

    The proposed construction access route from the nearest highway;

    (h)

    A statement by a professional engineer registered in California certifying that the rotor and overspeed controls have been designed and fabricated for the proposed use in accordance with good engineering practice.

(Ord. 85-39 § 4).