§ 88-3.806. Guarantees and security.
Responsibility. The reclamation plan shall state that the operator, applicant and permittee guarantee and accept responsibility for all reclamation work for a period of two years after completion of reclamation.
(b)
Performance Security. A cash deposit or surety bond shall be deposited to insure completion of reclamation work consistent with this article. The amount of security shall be determined by the zoning administrator and shall include all material and labor costs, adjusted for inflation to reflect anticipated total costs at the time of reclamation. Up to eighty percent of the cost of reclamation may be secured by assignment to the county of salvage rights for WECS apparatus.
(Ord. 85-39 § 4).